Electricity data access in District of Columbia
- Data access rule
- Commission order
“the Commission DIRECTS the Potomac Electric Power Company to provide a feasibility report for implementing Green Button Connect My Data in the District within 90 days” Order No. 20364, FC 1130, para. 94 [source]
- Citation
- Order No. 20364 (June 5, 2020), paras. 16 and 94
- Docket
- Formal Case No. 1130 (MEDSIS / PowerPath DC)
- Green Button required
- Not stated
- Automatic sharing (Connect My Data) required
- Not stated
- Customer can authorize a third party
- Not stated
- Utilities must allow device pairing
- Not stated
- Smart meter opt-out
- Not allowed
“denied a request from the Office of People's Counsel to reconsider an earlier decision that rejected calls to require Pepco to let customers opt out of its AMI program (summary)” Public Utilities Fortnightly, June 1, 2013 (secondary) [source]
- Effective
- 2020-06-05
“FORMAL CASE NO. 1130 ... Order No. 20364 ... June 5, 2020” Order No. 20364 [source]
- Source
- [source, unverified]
Pepco is the only electric distribution utility. Order No. 20364 directed Pepco only to file a Green Button Connect My Data feasibility report within 90 days (and to consider GBC for residential customers), not to implement it; later FC 1130 workgroup on GBCMD implementation reconvened 2021 (no implementing order found). Opt-out: per a 2013 trade-press report the PSC rejected OPC requests to require a Pepco AMI opt-out and denied reconsideration; no later order found (order number not located).
What District of Columbia utilities offer
| Utility | Interval | Green Button | Pair a device | SDR-readable |
|---|---|---|---|---|
| Potomac Electric Power Co | Hourly | Download My Data | Not stated | No |