Data access rule
Commission rule
“This subchapter sets forth requirements that electric distribution companies must follow in managing data created through the use of advanced metering infrastructure meters.” N.J.A.C. 14:5-10.1 [source]
Citation
N.J.A.C. 14:5-10 (AMI Data Access Standards), adopted R.2026 d.085, 58 N.J.R. 1845(a)
Docket
EX24090717 (rule); EO20110716 (AMI data access work session)
Green Button required
Yes
“Each EDC must make a customer's AMI data accessible and sharable using the Green Button Data Standard.” N.J.A.C. 14:5-10.4(c) [source]
Automatic sharing (Connect My Data) required
Yes
“Each EDC must enable Green Button Connect and/or Green Button Download as a means for customers or their authorized agents to access AMI data. ... AMI data sets must include a rolling 14 days' worth of AMI data delivered through supplier portals daily and accessible through an automated Application Programming Interface solution. EDCs must ensure AMI data is transmitted to the authorized third parties no later than 60 seconds after customer authorization.” N.J.A.C. 14:5-10.4(d)-(f) [source]
Customer can authorize a third party
Yes
“Customers may share their AMI data with authorized third parties through the Common Release Form at N.J.A.C. 14:5-10.6. Customers may revoke access to their AMI data from third parties at any time.” N.J.A.C. 14:5-10.4(b) [source]
Utilities must allow device pairing
Yes
“Upon customer request, EDCs must provide access to nonvalidated AMI data through a customer-owned, energymonitoring device that a customer may procure from the competitive market. ... The EDCs must configure the customer's AMI meter to allow the monitoring device to receive the customer's AMI data to as close to a real-time basis as allowable by the meter.” N.J.A.C. 14:5-10.3(b) [source]
Smart meter opt-out
Allowed, with a fee
“The recurring monthly fee for customers retaining their existing meter will be $12.00 and the one-time opt-out fee for the removal of an AMI meter and the re-installation of a conventional meter will be $45.00.” PSE&G CEF-EC Stipulation ¶31, BPU Docket EO18101115, Order 2021-01-07 [source]
Opt-out fees
Set per EDC in AMI stipulations approved by the BPU: PSE&G $12.00/month to keep existing meter + $45.00 one-time to remove an AMI meter (EO18101115, order 2021-01-07); ACE $15.00/month + $45.00 one-time (EO20080541, order 2021-07-14); JCP&L $15.00/month (existing meter or AMI meter with two-way comms disabled) + $44.46 one-time, no opt-out for net-metering or time-varying-rate customers (EO20080545, order 2022-02-23). Fees subject to review in later base rate cases. RECO not checked.
“The recurring monthly fee for customers retaining their existing meter will be $15.00, and the one-time opt-out fee for the removal of an AMI meter and the re-installation of a conventional meter will be $45.00.” ACE AMI Stipulation ¶32, BPU Docket EO20080541, Order 2021-07-14 [source]
“The monthly recurring fee for customers not participating in AMI meter reading shall be $15.00 ... The one-time fee for the removal of an AMI meter and re-installation of a conventional meter shall be $44.46.” JCP&L AMI Stipulation ¶39, BPU Docket EO20080545, Order 2022-02-23 [source]
Effective
2026-08-03
“Effective Date: August 3, 2026.” R.2026 d.085, 58 N.J.R. 1845(a) [source]
Source
[source]

Rule applies to electric distribution companies (the four IOUs: PSE&G, JCP&L, ACE, RECO); munis/co-ops not covered. Validated 15-minute (or finer) interval data within 48 h; Green Button data standard; 'Green Button Connect and/or Green Button Download' plus EDI and supplier-portal flat files for authorized third parties; automated API with rolling 14 days; data to third parties within 60 s of authorization; no fee for data access; NJ Common Release Form (one-click, MFA); Board staff to approve eligible third parties by Order; customer-owned energy-monitoring (HAN) device access to non-validated near-real-time data on request; 5-minute billing interval on request by PJM's FERC Order 2222 date. cmd_required=yes reflects the API/60-second automated third-party delivery mandate; the rule lets each EDC choose GB Connect and/or Download. Rule expires 2030-01-17. Pending bills A4786 (2024) / A2907 (2026) would bar opt-out fees (not verified).

What New Jersey utilities offer

UtilityIntervalGreen ButtonPair a deviceSDR-readable
Public Service Elec & Gas Co15 minutesNot statedNot statedNo
Jersey Central Power & Lt CoNot statedNot statedAvailableNot stated
Atlantic City Electric CoHourlyDownload My DataNot statedNot stated
Rockland Electric CoNot statedNot statedNot statedNot stated
City of Vineland - (NJ)Not statedNot stated
Sussex Rural Electric Coop IncNot statedNot statedNot statedNo
Borough of Butler - (NJ)Not statedNot statedNot statedNo
Borough of Madison - (NJ)
Borough of South River - (NJ)
Borough of Park Ridge - (NJ)
Seaside Heights Municipal Utility (NJ)
Borough of Milltown - (NJ)
Borough of Lavallette - (NJ)
Borough of Pemberton - (NJ)