Electricity data access in Rhode Island
- Data access rule
- Commission order
“Customer Portal: Company will maintain a customer portal. At a minimum, there should be no discontinuity of customers' ability to access account information and pay bills online.” Docket 22-49-EL Open Meeting Motion 12 (2023-09-27) [source]
- Citation
- Open Meeting Motions and Votes on the AMF Business Case (2023-09-27), Motions 12-13; written Report and Order No. 25353 (2025-05-20)
- Docket
- 22-49-EL; 25-19-EL (GBC/HAN plans); 24-38-GE (opt-out tariff)
- Green Button required
- Yes
“Within two months of the start of meter installation, the company must file a Green Button Connect plan” Docket 22-49-EL Open Meeting Motion 13 (2023-09-27) [source]
- Automatic sharing (Connect My Data) required
- Yes
“g. Timeline for GBC certification and version of certification.” Docket 22-49-EL Open Meeting Motion 13 (2023-09-27) [source]
- Customer can authorize a third party
- Not stated
- Utilities must allow device pairing
- Yes
“Within two months of the start of meter installation, the company must file a Home Area Network plan that addresses the following: h. Version of bring-your-own-device that will be offered to customers” Docket 22-49-EL Open Meeting Motion 13 (2023-09-27) [source]
- Smart meter opt-out
- Allowed, with a fee
“Commissioner Revens moved to accept the Division's recommendation that the only residential customers be allowed to opt out of the AMR/AMF.” PUC Open Meeting Minutes 2024-12-19, Docket 24-38-GE [source]
- Opt-out fees
- Docket 24-38-GE tariff (approved 2024-12-19, effective 2025-01-01, fees assessed from AMF rollout): residential customers not exporting to the grid only; monthly manual meter-read charge proposed $13 -> $20; one-time electric changeout fee $36 for customers who opt out after their area's AMF deployment period; one charge if opting out of both gas and electric
“For those opting out, the monthly manual meter read charge was proposed to increase from $13.00 per month to $20.00 per month.” PUC Open Meeting Minutes 2024-12-19, Docket 24-38-GE [source]
- Effective
- 2023-09-27
“Move to find that there is a need for the Company to transition its electric distribution operations from the existing AMR-based metering system to a system that utilizes advanced metering functionality (AMF).” Docket 22-49-EL Open Meeting Motion 1 (2023-09-27) [source]
- Source
- [source]
Applies to Rhode Island Energy (Narragansett Electric), the only regulated electric distribution utility; Pascoag, Block Island and munis not covered. Motion 13 requires GBC and HAN (bring-your-own-device) plans within two months of meter installation start, reviewed in contested Docket 25-19-EL (pending 2026). Motion 3(c) scope includes customers connecting a home area network device (Sense) to the meter. Opt-out amounts are the proposed tariff figures in the minutes; the Commission approved the tariff with eligibility changes.
What Rhode Island utilities offer
| Utility | Interval | Green Button | Pair a device | SDR-readable |
|---|---|---|---|---|
| The Narragansett Electric Co | 15 minutes | Download and Connect My Data | Available | Not stated |
| Clear River Electric and Water District | Not stated | Not stated | Not stated | |
| Block Island Utility District |